Utility
Substation Rebuild — Northern Nevada
Scope
Full substation demolition, structural foundations, control house, protective relaying, SCADA integration, commissioning.
Challenge
Live-bus construction adjacent to energized distribution feeders serving critical load.
Solution
Phased outage plan with utility operations, temporary switching, and self-performed civil + electrical crews under one PM.
Result
Zero unplanned outages. On-schedule energization.
Discuss a Similar Project ↗
Renewable
Utility-Scale Solar Collection
Scope
MV collection system, inverter pads, DC combiner installation, POI substation electrical.
Challenge
Aggressive PPA milestone with tracker installation running in parallel.
Solution
Engineering-driven sequencing and pre-fab MV terminations delivered ahead of tracker mechanical crews.
Result
Commercial operation achieved on the PPA deadline.
Discuss a Similar Project ↗
Industrial
Industrial Facility Expansion
Scope
Site prep, foundations, structural steel electrical, MCC installation, process controls integration.
Challenge
Live production areas immediately adjacent to expansion tie-in.
Solution
Off-hours cut-overs coordinated with plant operations; controls staged and burned-in before final tie-in.
Result
Zero production loss during cut-over weekend.
Discuss a Similar Project ↗
Civil
Municipal Roadway & Underground
Scope
Roadway improvements, drainage, underground utilities, structural concrete, restoration.
Challenge
Maintaining commuter flow through active corridor.
Solution
Night work, phased traffic control, public communications with municipal staff.
Result
Delivered under budget with commendation from municipal engineering.
Discuss a Similar Project ↗
Electrical
Commercial EV Charging Hub
Scope
MV service, transformer pad, switchgear, DC fast-charging equipment installation, commissioning.
Challenge
Utility service upgrade coordination on constrained timeline.
Solution
Early engagement with utility, self-performed civil for pad and duct bank.
Result
Fully commissioned and operational for site grand opening.
Discuss a Similar Project ↗
Industrial
Mining Process Electrical Upgrade
Scope
MCC replacement, motor control programming, conveyor power, controls tie-in.
Challenge
Fixed shutdown window with no schedule flexibility.
Solution
Pre-staged switchgear, parallel crews, 24/7 execution with MSHA-experienced supervision.
Result
Facility restarted on-schedule after shutdown.
Discuss a Similar Project ↗
Electrical
Data Center Standby Power
Scope
Generator paralleling switchgear, UPS distribution, load bank testing, commissioning.
Challenge
Zero-downtime tie-in to a live facility.
Solution
Redundant temporary feeds, staged commissioning, coordinated with client ops.
Result
Successful integrated systems test with no service impact.
Discuss a Similar Project ↗
Concrete
Structural Concrete — Equipment Pads
Scope
Excavation, formwork, rebar, placement, and finishing for inverter and BESS equipment pads.
Challenge
Tight tolerances required for equipment anchor patterns.
Solution
Templated formwork and QA/QC on every placement.
Result
All pads accepted on first equipment mounting.
Discuss a Similar Project ↗
Commercial
Commercial Tenant Improvement — Fit-Out
Scope
Interior electrical, lighting, distribution, low-voltage rough-in, TCO support.
Challenge
Multiple trades in the space with fixed opening day.
Solution
Weekly pull-plan coordination and self-performed crews across trades.
Result
Opened on scheduled grand opening date.
Discuss a Similar Project ↗
Industrial
24/7 Facility Maintenance Program
Scope
Preventive maintenance, electrical testing, generator service, on-call emergency response.
Challenge
Facility cannot afford unplanned downtime.
Solution
Scheduled PM windows, condition-based testing, 24/7 emergency crew.
Result
Documented uptime improvements year-over-year.
Discuss a Similar Project ↗